The EPMO lead's remit — what the PMO governs, what it must never become, and how it earns standing rather than compliance. Use this to stand up or reform a PMO, decide what it should and should not control, judge whether it is adding value or overhead, or work out why teams route

LLM Mart · 0 points · 14 views 0 listing impressions 0 install-command copies
Virus-scanned Reviewed automatically before listing.

Full trust report

Download cbrock84-headcount-plugins_pmo_skills_head-of-pmo-98d1c17.zip · 3 KB
Part of cbrock84/headcount — 160 skills

Install

skills CLI npx skills add https://github.com/cbrock84/headcount/tree/main/plugins/pmo/skills/head-of-pmo
Claude Code claude plugin marketplace add https://llmmart.ai/marketplace.json && claude plugin install cbrock84-headcount@llmmart
Git git clone https://github.com/cbrock84/headcount.git

The skills CLI installs just this skill, for any of its supported agents. Claude Code installs the whole cbrock84/headcount collection as a plugin from our marketplace. Git is the plain clone.

Skill manifest

Head of the PMO

An enterprise PMO exists to make the organization's delivery capacity visible and to force the choices that capacity implies. It does not exist to collect status.

The two failure modes

Every PMO fails in one of two directions, and the remedy for each makes the other worse:

  • The reporting PMO. It aggregates status nobody acts on, and teams learn to write updates that survive review rather than updates that are true. Its meetings are attended and its findings ignored. This is the common one.
  • The controlling PMO. It owns delivery decisions that belong to the teams, becomes a queue everything waits in, and is routed around by anyone with the standing to do so.

The line that holds: the PMO owns which work proceeds and whether the organization can absorb it. Teams own how the work gets done.

What it governs

  • pmo:portfolio-governance — intake, prioritization against real capacity, stage gates that can stop things, and resource contention across projects
  • pmo:program-management and pmo:project-delivery — the delivery disciplines themselves
  • pmo:estimating-and-contingency — how a defensible number is produced, and how much reserve the portfolio actually needs
  • pmo:schedule-development-and-analysis — building a schedule from logic rather than dates, and interrogating one you inherited
  • pmo:dependency-and-risk-management — the seams between teams, where programs actually fail
  • pmo:benefits-realization — whether the value claimed at approval ever appeared
  • pmo:change-and-adoption — whether anyone uses what was delivered

Benefits and adoption are the two that make a PMO worth funding. A PMO that governs intake but never checks outcomes has only made the front door more expensive.

Reporting line, and why it matters

The EPMO reports to the COO, not into any function whose work it governs. A PMO housed inside the largest delivery organization will, over time, prioritize that organization's work — not through bad faith but through proximity.

It has no write surface over the departments it governs. Its authority is procedural: it runs the gate, it holds the capacity number, and it publishes what was decided.

Earning standing

A PMO is obeyed when it is useful and circumvented when it is ceremony. What makes it useful:

  • Say no visibly, and say why. A gate that has never stopped anything is a gate nobody respects.
  • Hold the capacity number and defend it. The PMO is usually the only function that can see the organization is committed past what it can deliver, and saying so is most of the job.
  • Kill things. Stopping a dead project releases capacity the whole portfolio needs, and organizations are structurally bad at it — see pmo:portfolio-governance.
  • Make reporting cost less than it returns. Every status template is a tax on delivery. Ask for what changes a decision and nothing else.

Green until it is red

The standard status report fails in a specific way: projects report green until the week they cannot, then go straight to red. Nobody lied — each week's slip was individually recoverable, and admitting amber invites attention nobody wants.

Fix it by asking for facts rather than colors. What was due this week and did it land, has the critical path moved, what is the team blocked on. A status built from observable events cannot be optimistic, and the trend appears before the crisis.

Make amber cheap. If reporting trouble reliably produces help rather than scrutiny, it gets reported early, which is the entire value of a status process.

Estimates and the padding equilibrium

Teams pad when estimates are treated as commitments and used against them; leaders discount because they know it is padded; teams pad more. The equilibrium is that nobody knows how long anything takes and both sides are cynical about the number.

Break it by separating the estimate from the commitment. An estimate is a range with the uncertainty stated; a commitment is a date someone accepts accountability for, made with buffer held visibly at the portfolio level rather than hidden inside every task.

Track actuals against estimates for the team's own use, never as a performance measure. The moment it appears in a review, the padding returns and the data becomes worthless.

Sources

references/sources.md in this skill lists the outside authorities that settle the questions here — what each one is authoritative for, and what you may do with it. Check them before answering on anything they cover, and cite what you used. Most are free to read and not free to reproduce; the use note on each is binding.

Never

  • Collect status that feeds no decision.
  • Take a delivery decision that belongs to the team doing the work.
  • Run a portfolio gate that has never stopped anything.
  • Let the PMO report into the function whose work it governs.
  • Accept a status color without the facts that produced it.
  • Use estimate accuracy as a performance measure.
Files (headcount)
  • references
    • sources.md 895 B
      # Sources — `pmo:head-of-pmo`
      
      <!-- Generated by scripts/build-sources.py from sources/*.toml. Do not edit. -->
      
      Check these before answering on anything they cover, and cite what you used. The use note on each one is binding: most of what a professional cites is free to read and not free to reproduce.
      
      ## GAO Agile Assessment Guide
      
      US Government Accountability Office · US · public domain (US government) — quote freely
      
      <https://www.gao.gov/products/gao-24-105506>
      
      **Authoritative for:** Whether an organization has actually adopted an iterative delivery model or relabeled a staged one. Gives testable criteria, which is rare in this area, and reconciles iterative delivery with cost and schedule assurance.
      
      ---
      
      Sources are maintained in `sources/` upstream, not here. If one is wrong, out of date, or missing, fix it there — this file is regenerated and an edit to it is lost.
      
  • SKILL.md 5.3 KB
    ---
    name: head-of-pmo
    description: The EPMO lead's remit — what the PMO governs, what it must never become, and how it earns standing rather than compliance. Use this to stand up or reform a PMO, decide what it should and should not control, judge whether it is adding value or overhead, or work out why teams route around it.
    ---
    
    # Head of the PMO
    
    An enterprise PMO exists to make the organization's delivery capacity visible and to force the
    choices that capacity implies. It does not exist to collect status.
    
    ## The two failure modes
    
    Every PMO fails in one of two directions, and the remedy for each makes the other worse:
    
    - **The reporting PMO.** It aggregates status nobody acts on, and teams learn to write updates that
      survive review rather than updates that are true. Its meetings are attended and its findings
      ignored. This is the common one.
    - **The controlling PMO.** It owns delivery decisions that belong to the teams, becomes a queue
      everything waits in, and is routed around by anyone with the standing to do so.
    
    The line that holds: the PMO owns **which** work proceeds and **whether the organization can absorb
    it**. Teams own **how** the work gets done.
    
    ## What it governs
    
    - `pmo:portfolio-governance` — intake, prioritization against real capacity, stage gates that can
      stop things, and resource contention across projects
    - `pmo:program-management` and `pmo:project-delivery` — the delivery disciplines themselves
    - `pmo:estimating-and-contingency` — how a defensible number is produced, and how much reserve
      the portfolio actually needs
    - `pmo:schedule-development-and-analysis` — building a schedule from logic rather than dates, and
      interrogating one you inherited
    - `pmo:dependency-and-risk-management` — the seams between teams, where programs actually fail
    - `pmo:benefits-realization` — whether the value claimed at approval ever appeared
    - `pmo:change-and-adoption` — whether anyone uses what was delivered
    
    Benefits and adoption are the two that make a PMO worth funding. A PMO that governs intake but never
    checks outcomes has only made the front door more expensive.
    
    ## Reporting line, and why it matters
    
    The EPMO reports to the COO, not into any function whose work it governs. A PMO housed inside the
    largest delivery organization will, over time, prioritize that organization's work — not through bad
    faith but through proximity.
    
    It has no write surface over the departments it governs. Its authority is procedural: it runs the
    gate, it holds the capacity number, and it publishes what was decided.
    
    ## Earning standing
    
    A PMO is obeyed when it is useful and circumvented when it is ceremony. What makes it useful:
    
    - **Say no visibly, and say why.** A gate that has never stopped anything is a gate nobody respects.
    - **Hold the capacity number and defend it.** The PMO is usually the only function that can see the
      organization is committed past what it can deliver, and saying so is most of the job.
    - **Kill things.** Stopping a dead project releases capacity the whole portfolio needs, and
      organizations are structurally bad at it — see `pmo:portfolio-governance`.
    - **Make reporting cost less than it returns.** Every status template is a tax on delivery. Ask for
      what changes a decision and nothing else.
    
    ## Green until it is red
    
    The standard status report fails in a specific way: projects report green until the week they
    cannot, then go straight to red. Nobody lied — each week's slip was individually recoverable, and
    admitting amber invites attention nobody wants.
    
    Fix it by asking for facts rather than colors. What was due this week and did it land, has the
    critical path moved, what is the team blocked on. A status built from observable events cannot be
    optimistic, and the trend appears before the crisis.
    
    Make amber cheap. If reporting trouble reliably produces help rather than scrutiny, it gets
    reported early, which is the entire value of a status process.
    
    ## Estimates and the padding equilibrium
    
    Teams pad when estimates are treated as commitments and used against them; leaders discount because
    they know it is padded; teams pad more. The equilibrium is that nobody knows how long anything
    takes and both sides are cynical about the number.
    
    Break it by separating the estimate from the commitment. An estimate is a range with the
    uncertainty stated; a commitment is a date someone accepts accountability for, made with buffer
    held visibly at the portfolio level rather than hidden inside every task.
    
    Track actuals against estimates for the team's own use, never as a performance measure. The moment
    it appears in a review, the padding returns and the data becomes worthless.
    
    ## Sources
    
    `references/sources.md` in this skill lists the outside authorities that settle the questions
    here — what each one is authoritative for, and what you may do with it. Check them before
    answering on anything they cover, and cite what you used. Most are free to read and not free
    to reproduce; the use note on each is binding.
    
    ## Never
    
    - Collect status that feeds no decision.
    - Take a delivery decision that belongs to the team doing the work.
    - Run a portfolio gate that has never stopped anything.
    - Let the PMO report into the function whose work it governs.
    - Accept a status color without the facts that produced it.
    - Use estimate accuracy as a performance measure.
    