Claude Skill

technical-project-management

Manage technical projects from initiation through delivery and closure: choose and tailor predictive, iterative, Scrum, flow-based, or hybrid approaches; coordinate teams and vendors; track milestones, risks, issues, dependencies, forecasts, scope changes, and recovery. Use when

LLM Mart · 0 points · 9 views 0 listing impressions 0 install-command copies
Download magnus919-agent-skills-technical-project-management-d0edebb.zip · 57 KB

Install

skills CLI npx skills add https://github.com/magnus919/agent-skills/tree/main/technical-project-management
Claude Code claude plugin marketplace add https://llmmart.ai/marketplace.json && claude plugin install magnus919-agent-skills@llmmart
Git git clone https://github.com/magnus919/agent-skills.git

The skills CLI installs just this skill, for any of its supported agents. Claude Code installs the whole magnus919/agent-skills collection as a plugin from our marketplace. Git is the plain clone.

README

Technical Project Management

Keep technical projects moving with credible commitments, clear decisions, and useful evidence.

Why Install This Skill

A team can have good engineers and a busy board while still missing dependencies, hiding schedule risk, or leaving decisions unresolved. This skill helps your agent coordinate the work from project kickoff through acceptance and operational handoff. It selects an approach that fits your constraints instead of imposing one framework.

Teams without a project manager get a lightweight way to organize ownership and next steps. Experienced TPMs get concise analysis, recovery options, and decision briefs without introductory lessons. Research references and real cases explain where practices help and where their assumptions break down.

What You Get

Contents What they provide
SKILL.md Focused entry point and connections to specialist skills
references/ Method selection, predictive/adaptive/hybrid delivery, control, forecasting, recovery, closure, source ledger, and four real cases
templates/ Seven adaptable project records and a worked schedule input
scripts/ Read-only dependency schedule analysis with resource-conflict warnings and tests
evals/ Realistic quality scenarios covering team and expert use

Quick Start

Ask: "We have three teams, a fixed launch date, and a vendor slipping. Help me assess the impact and prepare a decision for our sponsor."

For a schedule calculation, from this directory:

python3 scripts/schedule.py --input templates/schedule-example.json --json

The example returns a finish at working day 6, one day beyond its deadline, and a shared-resource conflict. It does not claim those earliest dates are achievable.

Triggers

  • Starting or inheriting a technical project, including teams without a PM.
  • Choosing a delivery approach or coordinating teams and suppliers.
  • Reviewing milestones, forecasts, scope changes, or troubled-project recovery.
  • Preparing a sponsor decision or closing and handing off a project.

Requirements

No service, API key, or runtime is needed for the guidance and templates. The optional calculator and its tests require Python 3.10+ with the standard library. Jira or Linear operations use the separate tool skills and their own credentials.

Skill manifest

Technical Project Management

Help a team make and maintain credible delivery commitments. Start at the user's current decision; do not restart a healthy project or impose a new methodology.

First move

Read existing project artifacts before asking questions. Identify the outcome, current phase, immediate decision, decision-maker, constraints, and evidence gaps. Infer experience from the request and artifacts; ask about preference only if it matters. For teams without a PM, provide a small usable working system and explain unfamiliar concepts in context. For experienced TPMs, lead with the delta, options, recommendation, and decision needed; omit introductory lessons.

Choose the entry point

Starting condition First action Primary output
New or inherited project with unclear mandate Read Engagement and initiation Proposed brief with authority and evidence gaps
Approved work with a delivery method but weak control Read Control and communication Current control record and decision brief
Slipping date, cost, scope, or dependency Read Forecasting and schedule analysis and Change and recovery Conditional forecast and recovery options
Cross-team, supplier, or mixed-method handoff Read Hybrid and dependencies Dependency agreement and acceptance evidence
Delivered work, retirement, or decommissioning with unresolved ownership or benefits Read Closure and transition Conditional closure, accepted transition, or decommissioning record
Technical uncertainty needs staged learning Read Adaptive delivery Evidence-backed decision among PoC, prototype, pilot, or stop; none alone proves production readiness
Forecast, deadline, or resource-feasibility question Read Forecasting and schedule analysis Conditional forecast stating model, assumptions, capacity, and feasibility limits
Material risk, issue, assumption, or decision needs control Read Control and communication Record with owner, signal/trigger, response, authority, and next review
A supplier or team handoff lacks readiness or acceptance evidence Read Hybrid and dependencies Agreement with provider, receiver, definition of ready, evidence, fallback, and escalation

Do not call a desired date a commitment, a forecast an acceptance, or a diagnostic brief an approved plan.

Before proposing a commitment, identify who can authorize scope, dates, capacity, acceptance, and external communication. Mark each as accepted, proposed, unknown, or disputed. Read-only diagnosis may proceed; external updates require authorization.

Operating loop

  1. Establish mandate and authority; separate approved commitments, forecasts, assumptions, and unknowns. A diagnostic or options brief can precede approval; do not turn it into an approved implementation plan.
  2. Select the smallest adequate management approach. Preserve effective existing practices and specify any changed decision rights, cadence, and handoffs.
  3. Reuse the implementation plan and maintain milestones, dependency commitments, remaining work, resource availability, risks, issues, and decisions.
  4. Compare evidence with the baseline and tolerances. Investigate contradictions; missing evidence means unknown, not green. Surface forecast changes immediately when material; do not wait for a scheduled report.
  5. Present feasible options when scope, capacity, cost, or dates conflict. Keep the baseline history; an authorized change is not permission to hide prior variance.
  6. Close only on acceptance and explicit residual ownership. Distinguish project closure, release readiness, service operation, and later benefit realization.

Reference routing

Read only what the current task requires. Each reference includes applicability, procedures, failure signals, and an observable exit.

A multi-project initiative with a shared outcome, cross-project dependencies, or program-level benefits belongs to technical-program-management; a single bounded project remains here.

Decision phase / situation Read Exit artifact or evidence
New or inherited project, no PM, expert collaboration Engagement and initiation Proposed brief with mandate, authority, and evidence gaps
Choosing or questioning a methodology Method selection Approach decision with adaptations and revisit trigger
Predictive planning, stages, tolerances, fixed constraints Predictive and stage governance Baseline, tolerances, and gate evidence
Scrum, iteration, incremental delivery, discovery uncertainty Adaptive delivery Learning/increment evidence and inspect/adapt decision
Flow, shared specialists, critical chain, appetite-based work Flow and constrained capacity Capacity/WIP or appetite decision with owner
Mixed methods, cross-team or vendor interfaces Hybrid and dependencies Dependency agreement and interface acceptance evidence
Estimates, forecasts, budgets, schedule model Forecasting and schedule analysis Conditional forecast with assumptions and feasibility limits
Weekly control, stakeholder disagreement, escalations Control and communication Status/update or decision brief with next checkpoint
Scope changes, troubled projects, recovery Change and recovery Change/recovery record preserving the baseline
Acceptance, cancellation, operational handoff Closure and transition Closure or transition record with residual owners
Real examples or transferability checks Case studies Source-limited analogy, not a guarantee
Research provenance, edition, evidence limits Source index Traceable evidence ledger
Skill purpose, coverage, research decisions Research brief Coverage and limitation record
Validation scope and behavioral evaluation protocol Evaluation guide Reproducible evaluation record

Templates and calculation

Adapt existing project documents rather than creating parallel sources of truth. Use only artifacts that answer a current decision.

Need Artifact
Establish mandate and working agreements Project brief
Explain method choice and adaptation Approach decision
Maintain milestones and evidence Project control record
Coordinate a supplier or receiving team Dependency agreement
Report a change and ask for a decision Status and decision brief
Assess scope changes or recovery options Change and recovery record
Accept, cancel, or transfer ownership Closure record
Calculate a small dependency network Example schedule

Run python3 scripts/schedule.py --input templates/schedule-example.json --json from this skill's directory when dependency arithmetic helps. Read forecasting first: the result is an unconstrained earliest schedule, not a commitment or a resource-leveled plan. The script only reads input and writes stdout/stderr. Run python3 -m unittest discover -s scripts -p 'test_*.py' for its tests.

When not to use

Authority and completion

This methodology prepares decisions. It does not invent stakeholder consent, assign accepted commitments on someone else's behalf, or approve risk. Updating external project systems or sending communications changes external state:

Confirm the target, scope, and rollback path before acting. Read-only discovery may proceed without confirmation.

Apply existing session authorization; do not ask repeatedly for the same scope. Destructive actions need an explicit directive. Keep prepared drafts visibly distinct from issued communications. Do not monitor people or turn activity counts into individual performance judgments.

Complete a requested management cycle when the artifact or update is delivered, claims have evidence or explicit uncertainty, and unresolved decisions have an accountable route and next review trigger. Do not imply ongoing monitoring without an authorized mechanism. If three diagnostic passes yield no new evidence, stop with the missing input and affected decision; do not manufacture certainty.

Files (agent-skills)
  • evals
    • samples
      • baseline-expert.md 2.2 KB
        Loading…
      • baseline-schedule.md 1.4 KB
        Loading…
      • baseline-team.md 2.2 KB
        Loading…
      • final-team-provenance.json 789 B
        Loading…
      • final-team.md 4.6 KB
        Loading…
      • with-skill-expert.md 2.5 KB
        Loading…
      • with-skill-schedule.md 1.9 KB
        Loading…
      • with-skill-team.md 3.6 KB
        Loading…
    • evals.json 8.6 KB
      Loading…
    • sample-review.md 3.8 KB
      Loading…
  • references
    • adaptive-delivery.md 3.2 KB
      Loading…
    • case-studies.md 4.1 KB
      Loading…
    • change-and-recovery.md 3.5 KB
      Loading…
    • closure-and-transition.md 2.5 KB
      Loading…
    • control-and-communication.md 3.5 KB
      Loading…
    • engagement-and-initiation.md 3.5 KB
      Loading…
    • evaluation-guide.md 2.9 KB
      Loading…
    • flow-and-capacity.md 2.9 KB
      Loading…
    • forecasting.md 4.9 KB
      Loading…
    • hybrid-and-dependencies.md 3.3 KB
      Loading…
    • method-selection.md 4.1 KB
      Loading…
    • predictive-and-stages.md 3 KB
      Loading…
    • research-brief.md 3.9 KB
      Loading…
    • source-index.md 6.1 KB
      Loading…
  • scripts
    • schedule.py 7.3 KB
      Loading…
    • test_schedule.py 6.7 KB
      Loading…
  • templates
    • approach-decision.md 1.1 KB
      Loading…
    • change-and-recovery.md 1.1 KB
      Loading…
    • closure-record.md 1 KB
      Loading…
    • dependency-agreement.md 854 B
      Loading…
    • project-brief.md 1.5 KB
      Loading…
    • project-control.md 1.5 KB
      Loading…
    • schedule-example.json 400 B
      Loading…
    • status-and-decision.md 920 B
      Loading…
  • README.md 2.3 KB
    # Technical Project Management
    
    Keep technical projects moving with credible commitments, clear decisions, and useful evidence.
    
    ## Why Install This Skill
    
    A team can have good engineers and a busy board while still missing dependencies,
    hiding schedule risk, or leaving decisions unresolved. This skill helps your agent
    coordinate the work from project kickoff through acceptance and operational handoff.
    It selects an approach that fits your constraints instead of imposing one framework.
    
    Teams without a project manager get a lightweight way to organize ownership and
    next steps. Experienced TPMs get concise analysis, recovery options, and decision
    briefs without introductory lessons. Research references and real cases explain
    where practices help and where their assumptions break down.
    
    ## What You Get
    
    | Contents | What they provide |
    |---|---|
    | `SKILL.md` | Focused entry point and connections to specialist skills |
    | `references/` | Method selection, predictive/adaptive/hybrid delivery, control, forecasting, recovery, closure, source ledger, and four real cases |
    | `templates/` | Seven adaptable project records and a worked schedule input |
    | `scripts/` | Read-only dependency schedule analysis with resource-conflict warnings and tests |
    | `evals/` | Realistic quality scenarios covering team and expert use |
    
    ## Quick Start
    
    Ask: "We have three teams, a fixed launch date, and a vendor slipping. Help me
    assess the impact and prepare a decision for our sponsor."
    
    For a schedule calculation, from this directory:
    
    ```sh
    python3 scripts/schedule.py --input templates/schedule-example.json --json
    ```
    
    The example returns a finish at working day 6, one day beyond its deadline, and a
    shared-resource conflict. It does not claim those earliest dates are achievable.
    
    ## Triggers
    
    - Starting or inheriting a technical project, including teams without a PM.
    - Choosing a delivery approach or coordinating teams and suppliers.
    - Reviewing milestones, forecasts, scope changes, or troubled-project recovery.
    - Preparing a sponsor decision or closing and handing off a project.
    
    ## Requirements
    
    No service, API key, or runtime is needed for the guidance and templates. The
    optional calculator and its tests require Python 3.10+ with the standard library.
    Jira or Linear operations use the separate tool skills and their own credentials.
    
  • SKILL.md 11.5 KB
    ---
    name: technical-project-management
    description: >-
      Manage technical projects from initiation through delivery and closure: choose
      and tailor predictive, iterative, Scrum, flow-based, or hybrid approaches;
      coordinate teams and vendors; track milestones, risks, issues, dependencies,
      forecasts, scope changes, and recovery. Use when a team has no project manager,
      a TPM needs decision-ready analysis, a project is slipping, or commitments and
      handoffs need coordination. Use `technical-program-management` instead when
      multiple related projects, teams, vendors, shared capacity, or benefits must be
      coordinated toward one outcome. Adapt depth to the user's expertise. Do not use for
      a standalone coding task, product discovery or strategy, only writing an
      implementation plan, only diagnosing Kanban flow, operating a ticket tool,
      incident command, or a release go/no-go decision; route those to specialists.
    license: MIT
    compatibility: >-
      Host-neutral methodology and Markdown templates. Optional read-only schedule
      analysis requires Python 3.10+ standard library; no credentials or network.
    ---
    
    # Technical Project Management
    
    Help a team make and maintain credible delivery commitments. Start at the user's
    current decision; do not restart a healthy project or impose a new methodology.
    
    ## First move
    
    Read existing project artifacts before asking questions. Identify the outcome,
    current phase, immediate decision, decision-maker, constraints, and evidence gaps.
    Infer experience from the request and artifacts; ask about preference only if it
    matters. For teams without a PM, provide a small usable working system and explain
    unfamiliar concepts in context. For experienced TPMs, lead with the delta, options,
    recommendation, and decision needed; omit introductory lessons.
    
    ### Choose the entry point
    
    | Starting condition | First action | Primary output |
    |---|---|---|
    | New or inherited project with unclear mandate | Read [Engagement and initiation](references/engagement-and-initiation.md) | Proposed brief with authority and evidence gaps |
    | Approved work with a delivery method but weak control | Read [Control and communication](references/control-and-communication.md) | Current control record and decision brief |
    | Slipping date, cost, scope, or dependency | Read [Forecasting and schedule analysis](references/forecasting.md) and [Change and recovery](references/change-and-recovery.md) | Conditional forecast and recovery options |
    | Cross-team, supplier, or mixed-method handoff | Read [Hybrid and dependencies](references/hybrid-and-dependencies.md) | Dependency agreement and acceptance evidence |
    | Delivered work, retirement, or decommissioning with unresolved ownership or benefits | Read [Closure and transition](references/closure-and-transition.md) | Conditional closure, accepted transition, or decommissioning record |
    | Technical uncertainty needs staged learning | Read [Adaptive delivery](references/adaptive-delivery.md) | Evidence-backed decision among PoC, prototype, pilot, or stop; none alone proves production readiness |
    | Forecast, deadline, or resource-feasibility question | Read [Forecasting and schedule analysis](references/forecasting.md) | Conditional forecast stating model, assumptions, capacity, and feasibility limits |
    | Material risk, issue, assumption, or decision needs control | Read [Control and communication](references/control-and-communication.md) | Record with owner, signal/trigger, response, authority, and next review |
    | A supplier or team handoff lacks readiness or acceptance evidence | Read [Hybrid and dependencies](references/hybrid-and-dependencies.md) | Agreement with provider, receiver, definition of ready, evidence, fallback, and escalation |
    
    Do not call a desired date a commitment, a forecast an acceptance, or a diagnostic brief an approved plan.
    
    > Before proposing a commitment, identify who can authorize scope, dates, capacity, acceptance, and external communication. Mark each as accepted, proposed, unknown, or disputed. Read-only diagnosis may proceed; external updates require authorization.
    
    ## Operating loop
    
    1. Establish mandate and authority; separate approved commitments, forecasts,
       assumptions, and unknowns. A diagnostic or options brief can precede approval;
       do not turn it into an approved implementation plan.
    2. Select the smallest adequate management approach. Preserve effective existing
       practices and specify any changed decision rights, cadence, and handoffs.
    3. Reuse the implementation plan and maintain milestones, dependency commitments,
       remaining work, resource availability, risks, issues, and decisions.
    4. Compare evidence with the baseline and tolerances. Investigate contradictions;
       missing evidence means unknown, not green. Surface forecast changes immediately
       when material; do not wait for a scheduled report.
    5. Present feasible options when scope, capacity, cost, or dates conflict. Keep the
       baseline history; an authorized change is not permission to hide prior variance.
    6. Close only on acceptance and explicit residual ownership. Distinguish project
       closure, release readiness, service operation, and later benefit realization.
    
    ## Reference routing
    
    Read only what the current task requires. Each reference includes applicability,
    procedures, failure signals, and an observable exit.
    
    A multi-project initiative with a shared outcome, cross-project dependencies, or
    program-level benefits belongs to `technical-program-management`; a single bounded
    project remains here.
    
    | Decision phase / situation | Read | Exit artifact or evidence |
    |---|---|---|
    | New or inherited project, no PM, expert collaboration | [Engagement and initiation](references/engagement-and-initiation.md) | Proposed brief with mandate, authority, and evidence gaps |
    | Choosing or questioning a methodology | [Method selection](references/method-selection.md) | Approach decision with adaptations and revisit trigger |
    | Predictive planning, stages, tolerances, fixed constraints | [Predictive and stage governance](references/predictive-and-stages.md) | Baseline, tolerances, and gate evidence |
    | Scrum, iteration, incremental delivery, discovery uncertainty | [Adaptive delivery](references/adaptive-delivery.md) | Learning/increment evidence and inspect/adapt decision |
    | Flow, shared specialists, critical chain, appetite-based work | [Flow and constrained capacity](references/flow-and-capacity.md) | Capacity/WIP or appetite decision with owner |
    | Mixed methods, cross-team or vendor interfaces | [Hybrid and dependencies](references/hybrid-and-dependencies.md) | Dependency agreement and interface acceptance evidence |
    | Estimates, forecasts, budgets, schedule model | [Forecasting and schedule analysis](references/forecasting.md) | Conditional forecast with assumptions and feasibility limits |
    | Weekly control, stakeholder disagreement, escalations | [Control and communication](references/control-and-communication.md) | Status/update or decision brief with next checkpoint |
    | Scope changes, troubled projects, recovery | [Change and recovery](references/change-and-recovery.md) | Change/recovery record preserving the baseline |
    | Acceptance, cancellation, operational handoff | [Closure and transition](references/closure-and-transition.md) | Closure or transition record with residual owners |
    | Real examples or transferability checks | [Case studies](references/case-studies.md) | Source-limited analogy, not a guarantee |
    | Research provenance, edition, evidence limits | [Source index](references/source-index.md) | Traceable evidence ledger |
    | Skill purpose, coverage, research decisions | [Research brief](references/research-brief.md) | Coverage and limitation record |
    | Validation scope and behavioral evaluation protocol | [Evaluation guide](references/evaluation-guide.md) | Reproducible evaluation record |
    
    ## Templates and calculation
    
    Adapt existing project documents rather than creating parallel sources of truth.
    Use only artifacts that answer a current decision.
    
    | Need | Artifact |
    |---|---|
    | Establish mandate and working agreements | [Project brief](templates/project-brief.md) |
    | Explain method choice and adaptation | [Approach decision](templates/approach-decision.md) |
    | Maintain milestones and evidence | [Project control record](templates/project-control.md) |
    | Coordinate a supplier or receiving team | [Dependency agreement](templates/dependency-agreement.md) |
    | Report a change and ask for a decision | [Status and decision brief](templates/status-and-decision.md) |
    | Assess scope changes or recovery options | [Change and recovery record](templates/change-and-recovery.md) |
    | Accept, cancel, or transfer ownership | [Closure record](templates/closure-record.md) |
    | Calculate a small dependency network | [Example schedule](templates/schedule-example.json) |
    
    Run `python3 scripts/schedule.py --input templates/schedule-example.json --json`
    from this skill's directory when dependency arithmetic helps. Read forecasting
    first: the result is an unconstrained earliest schedule, not a commitment or a
    resource-leveled plan. The script only reads input and writes stdout/stderr.
    Run `python3 -m unittest discover -s scripts -p 'test_*.py'` for its tests.
    
    ## When not to use
    
    - A coding fix or architecture design: use the applicable engineering skill.
    - Validating needs or choosing product investments: use
      [product-discovery](../product-discovery/SKILL.md) or
      [product-roadmapping-and-portfolio](../product-roadmapping-and-portfolio/SKILL.md).
    - Only decomposing an approved requirement: use
      [implementation-planning](../implementation-planning/SKILL.md).
    - Detailed board, WIP, or service-flow diagnosis: use
      [kanban-guru](../kanban-guru/SKILL.md).
    - Shaping a bounded product bet: use [product-shaping](../product-shaping/SKILL.md).
    - Product-wide decision rights: use
      [product-operations-and-governance](../product-operations-and-governance/SKILL.md).
    - Executive-office support: use
      [chief-of-staff-methodology](../chief-of-staff-methodology/SKILL.md).
    - Release mechanics or launch approval: use
      [release-engineering](../release-engineering/SKILL.md) and
      [production-readiness](../production-readiness/SKILL.md). This skill may track project implications after that decision, but does not approve the release.
    - Live incident command: use
      [site-reliability-engineering](../site-reliability-engineering/SKILL.md).
    - Ticket operations alone: use [jira](../jira/SKILL.md) or
      [linear](../linear/SKILL.md). Use [financial-modeling](../financial-modeling/SKILL.md)
      for financial model construction, and [legal-strategy](../legal-strategy/SKILL.md)
      for contract interpretation.
    
    ## Authority and completion
    
    This methodology prepares decisions. It does not invent stakeholder consent,
    assign accepted commitments on someone else's behalf, or approve risk. Updating
    external project systems or sending communications changes external state:
    
    > Confirm the target, scope, and rollback path before acting. Read-only discovery may proceed without confirmation.
    
    Apply existing session authorization; do not ask repeatedly for the same scope.
    Destructive actions need an explicit directive. Keep prepared drafts visibly distinct
    from issued communications. Do not monitor people or turn activity counts into
    individual performance judgments.
    
    Complete a requested management cycle when the artifact or update is delivered,
    claims have evidence or explicit uncertainty, and unresolved decisions have an
    accountable route and next review trigger. Do not imply ongoing monitoring without
    an authorized mechanism. If three diagnostic passes yield no new evidence, stop
    with the missing input and affected decision; do not manufacture certainty.
    