sprint-planning
Use when planning sprint content, prioritizing stories within milestones, estimating capacity, or analyzing dependency graphs between stories. Covers MoSCoW prioritization, milestone management, velocity tracking, and dependency resolution for GitHub-based workflows.
Install
npx skills add https://github.com/SebastienDegodez/skraft-plugin/tree/main/plugins/skraft-backlog/skills/sprint-planning
claude plugin marketplace add https://llmmart.ai/marketplace.json && claude plugin install sebastiendegodez-skraft-plugin@llmmart
git clone https://github.com/SebastienDegodez/skraft-plugin.git
The skills CLI installs just this skill, for any of its supported agents. Claude Code installs the whole sebastiendegodez/skraft-plugin collection as a plugin from our marketplace. Git is the plain clone.
Skill manifest
Sprint Planning
Overview
Sprint planning decides which stories enter a milestone and in what order. Input: a list of DoR-approved stories from DISCUSS. Output: a prioritised, capacity-bounded, dependency-resolved sprint plan.
A sprint plan answers three questions:
- What enters this milestone? (MoSCoW prioritization)
- How much fits? (capacity check)
- In what order? (dependency sequencing)
MoSCoW Prioritization
Assign one MoSCoW label to every story before placing it in a milestone.
Priority Levels
| Level | Label | Definition | Capacity rule |
|---|---|---|---|
| Must Have | priority/must |
No sprint value delivered without it. Legal compliance, core user journey, removes a blocker. | Must-Haves fill ≤ 60% of sprint capacity. |
| Should Have | priority/should |
High value but a workaround exists. Would significantly improve user experience. | Should-Haves fill ≤ 30% of sprint capacity. |
| Could Have | priority/could |
Nice-to-have. Easy to cut without impacting the core sprint goal. | Could-Haves fill the remaining capacity. First items cut if overloaded. |
| Won't Have | priority/wont |
Explicitly out of scope for this sprint. Documented to avoid re-discussion. | Not scheduled. |
Application Steps
For each story, ask: "Can the sprint goal be achieved without this story?"
- No → Must Have
- Yes, but degraded → Should Have
- Yes, no degradation → Could Have
Fill capacity: Must-Haves first, then Should-Haves, then Could-Haves.
If Must-Haves alone exceed 60% of capacity: escalate to product owner for scope negotiation.
Auto-Insurance Domain Examples
| Story | MoSCoW | Reasoning |
|---|---|---|
| Driver eligibility check | Must Have | Core user journey — no application without eligibility |
| Driver profile form | Must Have | Required input for eligibility check |
| Eligibility certificate download | Should Have | Value: driver needs proof; workaround: manual email |
| Underwriter manual review flow | Should Have | Handles borderline cases; workaround: agent call |
| Dark mode for the portal | Could Have | UX improvement, no user journey impact |
| Policy cancellation flow | Won't Have | Deferred: not part of this milestone's theme |
Milestone Management
Naming Convention
v{major}.{minor}-{theme}
| Component | Rule | Example |
|---|---|---|
v{major} |
Increment on breaking changes or major scope shifts | v1 = first production release |
{minor} |
Increment per sprint / feature set | v0.2 = second pre-release sprint |
{theme} |
Lowercase kebab-case descriptor of the sprint goal | eligibility, driver-profile, payment |
Examples: v0.1-driver-profile, v0.2-eligibility, v0.3-document-upload, v1.0-launch
Milestone Scope
A well-scoped milestone:
- Contains 3–8 stories (fewer → unclear sprint goal; more → unmanageable)
- Spans 1–2 calendar weeks
- Has a clearly named theme that the entire team can articulate in one sentence
- Has a due date confirmed with stakeholders
When to create a new milestone vs extend current:
- New milestone: sprint theme shifts, previous milestone ships, more than 2 weeks of work remain
- Extend current: 1-2 stories slip by one day with same theme
GitHub Milestone Setup
Fields to populate for every milestone:
| Field | Content |
|---|---|
| Title | v{major}.{minor}-{theme} |
| Description | 2-3 sentences: sprint goal, key deliverables, non-goals |
| Due date | Confirmed sprint end date |
A milestone is "ready for DESIGN" when all its assigned stories are DoR-approved by the backlog-planner review gate and carry status/ready.
Dependency Analysis
Building the Dependency Graph
- Read the
Dependenciessection of each story - Build a directed adjacency list: Story A → depends on → Story B means "B must complete before A starts"
- Visualise as a DAG (Directed Acyclic Graph)
Example dependency graph for eligibility milestone:
STORY-01 (Personal Details)
↓
STORY-02 (Licence Validation) — depends on STORY-01
↓
STORY-03 (Eligibility Check) — depends on STORY-01, STORY-02
↓
STORY-04 (Document Upload) — depends on STORY-03
↓
STORY-05 (Payment) — depends on STORY-03, STORY-04
DAG Validation
A valid dependency graph is a DAG — no cycles. Perform depth-first search. If a back-edge is found, a cycle exists.
Cycle detection example (invalid):
STORY-03 → depends on → STORY-05
STORY-05 → depends on → STORY-03
→ Cycle: STORY-03 ↔ STORY-05. Neither can start. Must be resolved by splitting one story or removing the circular dependency.
Sequencing Rule
Deliver dependencies before dependents. Respect topological order when scheduling stories within a sprint:
- Stories with no dependencies: start on day 1
- Stories with one dependency: start after dependency is demo'd
- Stories with multiple dependencies: start after ALL dependencies are demo'd
Dependency Resolution
When a dependency cannot be resolved within the sprint (the dependency story is too large or not planned):
- Split the dependent story to remove the dependency (preferred)
- Move the dependent story to the next milestone
- Never start a story knowing its dependency will not be available
Capacity Heuristics
Sustainable Pace Formula
Available sprint capacity (story-days) = team_size × sprint_duration_days × 0.7
The 0.7 factor accounts for: standups, PR reviews, team meetings, unplanned incidents, context switching.
Example:
- Team: 3 engineers
- Sprint: 5 working days (1 week)
- Raw capacity: 3 × 5 = 15 engineer-days
- Sustainable capacity: 15 × 0.7 = 10.5 story-days
Story Points to Day Mapping
A plumbing convention, not a measurement. A point carries no duration; the bridge exists only because capacity arrives in days and the two units cannot be compared without one.
| Points | Story-days |
|---|---|
| 1 | 0.25 |
| 2 | 0.5 |
| 3 | 0.75 |
| 5 | 1.5 |
| 8 | 3.0 |
| 13 · 21 | ⛔ Stop — must split before entering sprint |
Cost per point never falls as the card grows: splitting an 8 into 3 + 5 costs 2.25 days instead of 3. Splitting is the cheaper arithmetic, never the more expensive one.
Sprint Capacity Check
Total scheduled story-days = Σ (story-days per story in sprint)
Sprint is valid if: total scheduled story-days ≤ sustainable capacity
Example check:
Sprint: v0.2-eligibility
Team: 3 engineers, 1 week → sustainable capacity: 10.5 story-days
Stories scheduled:
STORY-01 (Personal Details) — 2 → 0.5 days
STORY-02 (Licence Validation) — 3 → 0.75 days
STORY-03 (Eligibility Check) — 3 → 0.75 days
STORY-04 (Document Upload) — 3 → 0.75 days
STORY-05 (Payment) — 5 → 1.5 days
STORY-06 (Policy Confirmation) — 2 → 0.5 days
Total: 0.5 + 0.75 + 0.75 + 0.75 + 1.5 + 0.5 = 4.75 story-days ✅ (under 10.5)
Signs of Overloaded Sprint
- Total story-days > sustainable capacity
- All stories are Must Have (no flexibility to cut)
- 2+ L-sized stories in the same sprint
- A dependency chain that occupies the full sprint duration (no parallel work possible)
When overloaded:
- Cut Could-Haves first (move to next milestone)
- Cut Should-Haves second
- Split largest story if none of the above frees enough capacity
- Never cut Must-Haves without product owner approval
GitHub Conventions
Labels
Apply these labels to issues corresponding to stories:
| Category | Labels |
|---|---|
| Status | status/ready, status/in-progress, status/in-review, status/done, status/blocked |
| Priority | priority/must, priority/should, priority/could, priority/wont |
| Effort | effort/1, effort/2, effort/3, effort/5, effort/8 |
| Phase | phase/discuss, phase/design, phase/distill, phase/deliver |
Story Decomposition
If a story is split during DISCUSS, use GitHub sub-issues:
- Parent issue: the original story (labelled
effort/13oreffort/21before splitting) - Child issues: the split stories (each labelled with their own effort and status)
- Link parent to children using "Tracked by" relationship in GitHub Issues
Milestone Assignment
Assign each DoR-approved story's GitHub issue to the sprint milestone immediately after sprint planning. The milestone title must match the naming convention: v{major}.{minor}-{theme}.
References
- prioritization-matrix.md — MoSCoW table, value/effort matrix, scoring formula
- milestone-conventions.md — naming, scope, GitHub setup, readiness criteria
Files (skraft-plugin)
-
references
-
milestone-conventions.md 5.7 KB
Loading… -
prioritization-matrix.md 5.2 KB
Loading…
-
-
SKILL.md 8.8 KB
--- name: sprint-planning description: Use when planning sprint content, prioritizing stories within milestones, estimating capacity, or analyzing dependency graphs between stories. Covers MoSCoW prioritization, milestone management, velocity tracking, and dependency resolution for GitHub-based workflows. --- # Sprint Planning ## Overview Sprint planning decides which stories enter a milestone and in what order. Input: a list of DoR-approved stories from DISCUSS. Output: a prioritised, capacity-bounded, dependency-resolved sprint plan. A sprint plan answers three questions: 1. **What** enters this milestone? (MoSCoW prioritization) 2. **How much** fits? (capacity check) 3. **In what order?** (dependency sequencing) --- ## MoSCoW Prioritization Assign one MoSCoW label to every story before placing it in a milestone. ### Priority Levels | Level | Label | Definition | Capacity rule | |---|---|---|---| | **Must Have** | `priority/must` | No sprint value delivered without it. Legal compliance, core user journey, removes a blocker. | Must-Haves fill ≤ 60% of sprint capacity. | | **Should Have** | `priority/should` | High value but a workaround exists. Would significantly improve user experience. | Should-Haves fill ≤ 30% of sprint capacity. | | **Could Have** | `priority/could` | Nice-to-have. Easy to cut without impacting the core sprint goal. | Could-Haves fill the remaining capacity. First items cut if overloaded. | | **Won't Have** | `priority/wont` | Explicitly out of scope for this sprint. Documented to avoid re-discussion. | Not scheduled. | ### Application Steps 1. For each story, ask: "Can the sprint goal be achieved without this story?" - No → Must Have - Yes, but degraded → Should Have - Yes, no degradation → Could Have 2. Fill capacity: Must-Haves first, then Should-Haves, then Could-Haves. 3. If Must-Haves alone exceed 60% of capacity: escalate to product owner for scope negotiation. ### Auto-Insurance Domain Examples | Story | MoSCoW | Reasoning | |---|---|---| | Driver eligibility check | Must Have | Core user journey — no application without eligibility | | Driver profile form | Must Have | Required input for eligibility check | | Eligibility certificate download | Should Have | Value: driver needs proof; workaround: manual email | | Underwriter manual review flow | Should Have | Handles borderline cases; workaround: agent call | | Dark mode for the portal | Could Have | UX improvement, no user journey impact | | Policy cancellation flow | Won't Have | Deferred: not part of this milestone's theme | --- ## Milestone Management ### Naming Convention ``` v{major}.{minor}-{theme} ``` | Component | Rule | Example | |---|---|---| | `v{major}` | Increment on breaking changes or major scope shifts | `v1` = first production release | | `{minor}` | Increment per sprint / feature set | `v0.2` = second pre-release sprint | | `{theme}` | Lowercase kebab-case descriptor of the sprint goal | `eligibility`, `driver-profile`, `payment` | **Examples:** `v0.1-driver-profile`, `v0.2-eligibility`, `v0.3-document-upload`, `v1.0-launch` ### Milestone Scope A well-scoped milestone: - Contains 3–8 stories (fewer → unclear sprint goal; more → unmanageable) - Spans 1–2 calendar weeks - Has a clearly named theme that the entire team can articulate in one sentence - Has a due date confirmed with stakeholders **When to create a new milestone vs extend current:** - New milestone: sprint theme shifts, previous milestone ships, more than 2 weeks of work remain - Extend current: 1-2 stories slip by one day with same theme ### GitHub Milestone Setup Fields to populate for every milestone: | Field | Content | |---|---| | Title | `v{major}.{minor}-{theme}` | | Description | 2-3 sentences: sprint goal, key deliverables, non-goals | | Due date | Confirmed sprint end date | A milestone is "ready for DESIGN" when all its assigned stories are DoR-approved by the backlog-planner review gate and carry `status/ready`. --- ## Dependency Analysis ### Building the Dependency Graph 1. Read the `Dependencies` section of each story 2. Build a directed adjacency list: Story A → depends on → Story B means "B must complete before A starts" 3. Visualise as a DAG (Directed Acyclic Graph) ``` Example dependency graph for eligibility milestone: STORY-01 (Personal Details) ↓ STORY-02 (Licence Validation) — depends on STORY-01 ↓ STORY-03 (Eligibility Check) — depends on STORY-01, STORY-02 ↓ STORY-04 (Document Upload) — depends on STORY-03 ↓ STORY-05 (Payment) — depends on STORY-03, STORY-04 ``` ### DAG Validation A valid dependency graph is a DAG — no cycles. Perform depth-first search. If a back-edge is found, a cycle exists. **Cycle detection example (invalid):** ``` STORY-03 → depends on → STORY-05 STORY-05 → depends on → STORY-03 ``` → Cycle: STORY-03 ↔ STORY-05. Neither can start. Must be resolved by splitting one story or removing the circular dependency. ### Sequencing Rule Deliver dependencies before dependents. Respect topological order when scheduling stories within a sprint: 1. Stories with no dependencies: start on day 1 2. Stories with one dependency: start after dependency is demo'd 3. Stories with multiple dependencies: start after ALL dependencies are demo'd ### Dependency Resolution When a dependency cannot be resolved within the sprint (the dependency story is too large or not planned): 1. Split the dependent story to remove the dependency (preferred) 2. Move the dependent story to the next milestone 3. Never start a story knowing its dependency will not be available --- ## Capacity Heuristics ### Sustainable Pace Formula ``` Available sprint capacity (story-days) = team_size × sprint_duration_days × 0.7 ``` The 0.7 factor accounts for: standups, PR reviews, team meetings, unplanned incidents, context switching. **Example:** - Team: 3 engineers - Sprint: 5 working days (1 week) - Raw capacity: 3 × 5 = 15 engineer-days - Sustainable capacity: 15 × 0.7 = **10.5 story-days** ### Story Points to Day Mapping A plumbing convention, not a measurement. A point carries no duration; the bridge exists only because capacity arrives in days and the two units cannot be compared without one. | Points | Story-days | |---|---| | 1 | 0.25 | | 2 | 0.5 | | 3 | 0.75 | | 5 | 1.5 | | 8 | 3.0 | | 13 · 21 | ⛔ Stop — must split before entering sprint | Cost per point never falls as the card grows: splitting an 8 into 3 + 5 costs 2.25 days instead of 3. Splitting is the cheaper arithmetic, never the more expensive one. ### Sprint Capacity Check ``` Total scheduled story-days = Σ (story-days per story in sprint) Sprint is valid if: total scheduled story-days ≤ sustainable capacity ``` **Example check:** ``` Sprint: v0.2-eligibility Team: 3 engineers, 1 week → sustainable capacity: 10.5 story-days Stories scheduled: STORY-01 (Personal Details) — 2 → 0.5 days STORY-02 (Licence Validation) — 3 → 0.75 days STORY-03 (Eligibility Check) — 3 → 0.75 days STORY-04 (Document Upload) — 3 → 0.75 days STORY-05 (Payment) — 5 → 1.5 days STORY-06 (Policy Confirmation) — 2 → 0.5 days Total: 0.5 + 0.75 + 0.75 + 0.75 + 1.5 + 0.5 = 4.75 story-days ✅ (under 10.5) ``` ### Signs of Overloaded Sprint - Total story-days > sustainable capacity - All stories are Must Have (no flexibility to cut) - 2+ L-sized stories in the same sprint - A dependency chain that occupies the full sprint duration (no parallel work possible) **When overloaded:** 1. Cut Could-Haves first (move to next milestone) 2. Cut Should-Haves second 3. Split largest story if none of the above frees enough capacity 4. Never cut Must-Haves without product owner approval --- ## GitHub Conventions ### Labels Apply these labels to issues corresponding to stories: | Category | Labels | |---|---| | Status | `status/ready`, `status/in-progress`, `status/in-review`, `status/done`, `status/blocked` | | Priority | `priority/must`, `priority/should`, `priority/could`, `priority/wont` | | Effort | `effort/1`, `effort/2`, `effort/3`, `effort/5`, `effort/8` | | Phase | `phase/discuss`, `phase/design`, `phase/distill`, `phase/deliver` | ### Story Decomposition If a story is split during DISCUSS, use GitHub sub-issues: - Parent issue: the original story (labelled `effort/13` or `effort/21` before splitting) - Child issues: the split stories (each labelled with their own effort and status) - Link parent to children using "Tracked by" relationship in GitHub Issues ### Milestone Assignment Assign each DoR-approved story's GitHub issue to the sprint milestone immediately after sprint planning. The milestone title must match the naming convention: `v{major}.{minor}-{theme}`. --- ## References - [prioritization-matrix.md](references/prioritization-matrix.md) — MoSCoW table, value/effort matrix, scoring formula - [milestone-conventions.md](references/milestone-conventions.md) — naming, scope, GitHub setup, readiness criteria