Knowledge base from the GAO Cost Estimating and Assessment Guide (GAO-20-195G). Use for program cost estimating: the four characteristics of a reliable estimate (comprehensive, well documented, accurate, credible) and the 18 best practices; the 12-step cost estimating process (pu

LLM Mart · 0 points · 2 views 0 listing impressions 0 install-command copies
Download jgsystemsconsulting-jgs-se-knowledge-packs-packs_gao-cost-3bf1e13.zip · 82 KB

Install

skills CLI npx skills add https://github.com/jgsystemsconsulting/jgs-se-knowledge-packs/tree/main/packs/gao-cost
Claude Code claude plugin marketplace add https://llmmart.ai/marketplace.json && claude plugin install jgsystemsconsulting-jgs-se-knowledge-packs@llmmart
Git git clone https://github.com/jgsystemsconsulting/jgs-se-knowledge-packs.git

The skills CLI installs just this skill, for any of its supported agents. Claude Code installs the whole jgsystemsconsulting/jgs-se-knowledge-packs collection as a plugin from our marketplace. Git is the plain clone.

Skill manifest

GAO Cost Estimating and Assessment Guide (GAO-20-195G)

Source: GAO (US Government work, public domain) | Chapters: 8

When to use

Use this skill to develop, manage, or evaluate a program cost estimate: framing the estimate's purpose and scope, structuring it with a WBS, choosing estimating methods, turning a point estimate into a risk-adjusted budget, documenting and updating it, auditing it against GAO's reliability criteria, and connecting it to earned value management for execution. This is the cost-estimating companion to the GAO gao-schedule and gao-tra guides and the management-side counterpart to a program's life cycle cost estimate.

Prerequisites: none — plain Markdown; no MCP server, API key, or licence tier needed at runtime.

How to Use This Skill

  • Without arguments — load the core frameworks below: the four characteristics + 18 best practices, the 12-step process, the estimating methods, risk/uncertainty, EVM, and the specialized techniques.
  • With a topic — ask about a characteristic ("credible"), a step ("ground rules and assumptions", "point estimate"), a method ("parametric", "learning curve"), a risk concept ("Monte Carlo", "confidence level", "contingency"), or an EVM term ("CPI", "EAC", "performance measurement baseline").
  • With a chapter — ch02/ch03/ch05 (the 12 steps), ch04 (risk/uncertainty), ch06 (auditing), ch07 (EVM), ch08 (specialized techniques).

Supporting files: glossary.md, patterns.md, cheatsheet.md.

One discipline, two uses. The Guide is both an authoring standard (how to build a reliable estimate) and an audit standard (how to grade one). The same four characteristics and 18 best practices serve both. EVM (ch07) is the execution-side bridge: the estimate says what a program could cost; EVM measures whether it is delivering against a baseline built from that estimate.

Core Frameworks & Mental Models

What a cost estimate is — and why reliability is a process, not luck

A cost estimate is the sum of individual cost elements, built from established methods and valid data, projecting what a program will cost in the future given what is known now. It is not a one-time deliverable — managing it means revising it as actuals arrive, adjusting it when the program changes, and analyzing the gaps. The Guide's central claim: reliability is the predictable output of a disciplined, repeatable process, not seniority or luck. A reliable estimate matters structurally for government — every dollar committed to one program is denied to another, so an unrealistic estimate can ripple cuts across a whole portfolio.

The Four Characteristics of a Reliable Cost Estimate

GAO's research identifies four characteristics that a reliable estimate exhibits. They are the assessment yardstick auditors apply, and the design targets an estimator engineers toward:

Characteristic What it demands
Comprehensive full life cycle + complete scope (a complete WBS); all GR&As documented; nothing omitted or double-counted
Well documented sources, methods, and calculations captured so an unfamiliar analyst could rebuild it; traced to source data
Accurate unbiased (not optimistic or conservative); most-likely-cost basis; inflation-adjusted; reconciled to actuals
Credible limitations exposed via sensitivity and risk/uncertainty analysis; major drivers cross-checked; reconciled to an independent cost estimate (ICE)

The 18 best practices are the actionable steps that produce these characteristics; each best practice maps to one characteristic. An estimate that fully reflects all four is deemed reliable.

The 12-Step Cost Estimating Process

The procedural backbone, grouped into four phases:

  • Plan & define (Steps 1-4): (1) define the estimate's purpose — intended use fixes scope and detail; (2) develop the estimating plan — team, study plan, schedule; (3) define the program via a cost-free technical baseline description; (4) determine the estimating structure — the work breakdown structure (WBS), the product-oriented decomposition that ties cost, schedule, EVM, and risk together.
  • Build the number (Steps 5-7): (5) identify ground rules and assumptions (global + element-specific); (6) obtain the data — collect, validate, normalize (the most difficult, time-consuming step; data quality is the biggest lever); (7) develop the point estimate — select a method per WBS element, build the model, time-phase, sum, and cross-check against an ICE.
  • Quantify confidence (Steps 8-9): (8) sensitivity analysis (vary one input at a time); (9) risk and uncertainty analysis (vary many inputs together via simulation → probability distribution + confidence level).
  • Finalize & sustain (Steps 10-12): (10) document the estimate; (11) present it to management for formal approval (not finished until approved); (12) update it against actuals and program changes over the life cycle.

Each step's chapter closes with a "Survey of Step" — Process Tasks, Best Practices, and Likely Effects if criteria are not fully met — which is what makes each step auditable.

Estimating Methods

Choose by program maturity and available data; the method can differ per WBS element:

Method Use when Trade-off
Analogy early; a close similar system exists fast, low data; weak without a good analog
Parametric drivers + cost history, design still vague repeatable via cost estimating relationships (CERs); needs valid data range
Engineering build-up mature design most accurate; slow and data-hungry

Supplemented by expert opinion, extrapolation from actuals (averages, EACs), and learning curves (Y = AX^b) for recurring production.

Risk and Uncertainty → a risk-adjusted budget

A point estimate alone carries no confidence information and tends to under-fund. Sensitivity analysis isolates one input at a time (ranked on a tornado chart) to find what the estimate is most responsive to. Risk and uncertainty analysis lets inputs vary together — via the three-point method (min/most-likely/max) and/or the risk-driver method (probability × cost effect, from the risk register) — driven by Monte Carlo simulation, producing a total-cost probability distribution. Reading the cumulative distribution (S curve) gives a defensible confidence level; contingency is sized as the gap between the point estimate and that level.

Earned Value Management (EVM) — measuring execution

Spending data alone misleads (the railroad example: looks under-budget while badly behind). EVM adds the missing third number — the value of work performed. Three measures: BCWS (planned value), BCWP (earned value), ACWP (actual cost). Derived indexes: CPI = BCWP/ACWP (cost), SPI = BCWP/BCWS (schedule), TCPI (efficiency needed on remaining work). The EAC forecasts total cost from cumulative CPI. The estimate is converted into a time-phased performance measurement baseline (PMB); an integrated baseline review (IBR) confirms it is executable — the crucial link between cost estimating and EVM. EVM systems are validated against EIA-748's 32 guidelines. OMB requires EVM for major acquisitions with development effort.

Specialized Techniques & Internal Control

Beyond the 12 steps: software cost estimating (size first via SLOC/function points/COSMIC, convert to effort; classify code new/reused/adapted/auto-generated); learning curves (unit vs. cumulative-average theory; Anderlohr/retrograde for production breaks); Analysis of Alternatives (AOA) (22 best practices in 5 phases; NPV where benefits monetize); WBS templates (MIL-STD-881D, NASA/DOE/PMI handbooks); and the Green Book (GAO-14-704G) internal-control framework (5 components, 17 principles) — because the cost estimating process is itself an internal control.


Chapter Index

# Section Key content
ch01 Fundamentals & the four characteristics What a cost estimate is; reliability as process; the four characteristics; 18 best practices; 12-step process; LCCE; why government needs reliable estimates
ch02 Steps 1-4: Planning & program definition Purpose & scope; estimating plan/team; technical baseline description; the work breakdown structure (WBS)
ch03 Steps 5-7: Ground rules, data, point estimate Global vs. element-specific GR&As; data collection/validation/normalization; estimating methods (analogy/parametric/build-up); cross-checks and the ICE
ch04 Steps 8-9: Sensitivity, risk & uncertainty Sensitivity (one-at-a-time, tornado chart); three-point & risk-driver methods; Monte Carlo; S curve, confidence level, contingency
ch05 Steps 10-12: Document, present, update Documentation template & rationale; management approval; updating against actuals and program changes
ch06 Auditing & validating The characteristics/best practices as gradable criteria; mapping practices to characteristics; assessing agency guidance against the 12 steps; audit criteria & data collection
ch07 Earned value management EIA-748 (32 guidelines); 13 EVM activities; PMB/IBR/CPR; BCWS/BCWP/ACWP; CPI/SPI/TCPI; EAC; OTB/OTS; EVM system acceptance
ch08 Specialized techniques & internal control Software cost estimating; learning curves (Anderlohr/retrograde); WBS templates; TRLs; AOA (22 practices); the Green Book (5 components, 17 principles)

Topic Index

  • 18 best practices → ch01, ch06, cheatsheet
  • Accurate (characteristic) → ch01, ch06
  • Analogy method → ch03, cheatsheet
  • Analysis of Alternatives (AOA) → ch08, ch01
  • Anderlohr / retrograde (production break) → ch08
  • Audit / validation of an estimate → ch06, patterns
  • CPI / SPI / TCPI (performance indexes) → ch07, cheatsheet
  • Comprehensive (characteristic) → ch01, ch06
  • Confidence level / S curve → ch04, cheatsheet
  • Contingency / management reserve → ch04, ch07
  • Cost estimating relationship (CER) → ch03, ch04
  • Credible (characteristic) → ch01, ch06
  • Data collection / validation / normalization → ch03
  • Documentation (Step 10) → ch05, patterns
  • Earned value management (EVM) → ch07, ch01, cheatsheet
  • EIA-748 / 32 guidelines → ch07
  • Engineering build-up method → ch03, cheatsheet
  • Estimate at completion (EAC) → ch07
  • Four characteristics (reliable estimate) → ch01, ch06, cheatsheet
  • Green Book / internal control → ch08
  • Ground rules & assumptions (GR&A) → ch03
  • Independent cost estimate (ICE) → ch03, ch05
  • Integrated baseline review (IBR) → ch07, ch08
  • Learning curve (Y = AX^b) → ch08, ch03
  • Life cycle cost estimate (LCCE) → ch01, ch02
  • Monte Carlo simulation → ch04
  • Parametric method → ch03, cheatsheet
  • Performance measurement baseline (PMB) → ch07
  • Point estimate (Step 7) → ch03
  • Present / management approval (Step 11) → ch05
  • Risk & uncertainty analysis (Step 9) → ch04, cheatsheet
  • Risk driver / risk register → ch04
  • Sensitivity analysis (Step 8) → ch04, cheatsheet
  • Software cost estimating → ch08
  • Technical baseline description (Step 3) → ch02
  • Technology readiness level (TRL) → ch08
  • Three-point estimate → ch04
  • Tornado chart → ch04
  • 12-step process → ch02, ch03, ch04, ch05, cheatsheet
  • Update the estimate (Step 12) → ch05
  • Well documented (characteristic) → ch01, ch05, ch06
  • Work breakdown structure (WBS) → ch02, ch08
  • WBS templates (MIL-STD-881D, NASA/DOE/PMI) → ch08

Supporting Files

  • glossary.md — key cost-estimating, risk, and EVM terms, alphabetical, with chapter references
  • patterns.md — reusable patterns (run the 12 steps; engineer toward the four characteristics; pick a method by maturity; convert the point estimate to a risk-adjusted budget; document/update; audit; pair with EVM; specialized techniques) with When/How/Trade-offs
  • cheatsheet.md — the 12 steps, four-characteristics table, method-selection table, risk toolkit, EVM index reference, and tells & smells

Scope & Limits

Covers: program cost estimating per the GAO Cost Estimating and Assessment Guide (GAO-20-195G, March 2020) — the four characteristics of a reliable estimate and the 18 best practices; the full 12-step cost estimating process; estimating methods (analogy, parametric, engineering build-up, learning curves); sensitivity, risk, and uncertainty analysis (Monte Carlo, confidence levels, contingency); documenting, presenting, and updating; auditing/validating an estimate against the characteristics; earned value management (EIA-748, the EVM measures and indexes, PMB, IBR, EAC forecasting, system acceptance); and specialized techniques (software cost estimating, Analysis of Alternatives, WBS templates, technology readiness levels, the Green Book internal-control framework).

Thin on / does not cover in depth: schedule estimating and schedule risk analysis — the Guide deliberately hands these to the GAO Schedule Assessment Guide (GAO-16-89G; see gao-schedule), and technology-maturity assessment to the Technology Readiness Assessment Guide (GAO-20-48G; see gao-tra). It does not reproduce the full text of referenced standards and frameworks — EIA-748, MIL-STD-881D, the Green Book (GAO-14-704G), ICEAA/AACEI/PMI standards — these are named and summarized, not copied. Embedded source figures and tables (discipline maps, WBS diagrams, worked method tables, EVM exhibits) are described/paraphrased here, not reproduced; redraw from the originals if a rendered exhibit is needed. The Guide is GAO best-practice guidance, oriented to US federal acquisitions and DoD/NASA examples; it is not a regulation, though several statutes (Weapon Systems Acquisition Reform Act, Nunn-McCurdy, FASA, Clinger-Cohen, the FAR/DFARS EVM provisions) make parts of it effectively mandatory for major acquisitions.

Jurisdiction: US Government public domain work. The guidance is voluntary best practice but is broadly adopted and partly mandated for federal major acquisitions; it is adaptable to non-federal programs.

Files (jgs-se-knowledge-packs)
  • chapters
    • ch01-gao-cost-fundamentals-credible-estimates.md 19.3 KB
      Loading…
    • ch02-gao-cost-process-planning-program-definition.md 21.9 KB
      Loading…
    • ch03-gao-cost-data-ground-rules-point-estimate.md 25.8 KB
      Loading…
    • ch04-gao-cost-sensitivity-risk-uncertainty.md 21.3 KB
      Loading…
    • ch05-gao-cost-document-present-update.md 13.6 KB
      Loading…
    • ch06-gao-cost-auditing-validating.md 13 KB
      Loading…
    • ch07-gao-cost-earned-value-management.md 22.1 KB
      Loading…
    • ch08-gao-cost-specialized-techniques-internal-control.md 24 KB
      Loading…
  • cheatsheet.md 6.5 KB
    Loading…
  • glossary.md 9.1 KB
    Loading…
  • LICENSE 2 KB · in bundle
  • PACK.yaml 1.1 KB
    Loading…
  • patterns.md 8.8 KB
    Loading…
  • SKILL.md 16.1 KB
    ---
    name: gao-cost
    description: "Knowledge base from the GAO Cost Estimating and Assessment Guide (GAO-20-195G). Use for program cost estimating: the four characteristics of a reliable estimate (comprehensive, well documented, accurate, credible) and the 18 best practices; the 12-step cost estimating process (purpose, plan, technical baseline, WBS, ground rules and assumptions, data, point estimate, sensitivity, risk/uncertainty, document, present, update); estimating methods (analogy, parametric, engineering build-up, learning curves); Monte Carlo risk/uncertainty analysis, confidence levels and contingency; auditing and validating an estimate against the characteristics; earned value management (EIA-748, BCWS/BCWP/ACWP, CPI/SPI/TCPI, EAC, PMB, IBR); and specialized techniques (software cost estimating, learning curves, Analysis of Alternatives, WBS templates, the Green Book internal-control framework). This is the cost-estimating companion to the GAO Schedule and Technology Readiness Assessment guides. Does not cover schedule estimating/risk in depth (see the GAO Schedule Assessment Guide), agency-specific cost models, or the full text of referenced standards (EIA-748, MIL-STD-881D, the Green Book) — these are named, not reproduced."
    ---
    
    <!-- argument-hint: [characteristic, 12-step process step, estimating method, risk/uncertainty, EVM term, audit, software/learning-curve/AOA, chapter number] -->
    
    # GAO Cost Estimating and Assessment Guide (GAO-20-195G)
    **Source**: GAO (US Government work, public domain) | **Chapters**: 8
    
    ## When to use
    Use this skill to develop, manage, or evaluate a program **cost estimate**: framing the estimate's purpose and scope, structuring it with a WBS, choosing estimating methods, turning a point estimate into a risk-adjusted budget, documenting and updating it, auditing it against GAO's reliability criteria, and connecting it to **earned value management** for execution. This is the cost-estimating companion to the GAO `gao-schedule` and `gao-tra` guides and the management-side counterpart to a program's life cycle cost estimate.
    
    **Prerequisites:** none — plain Markdown; no MCP server, API key, or licence tier needed at runtime.
    
    ## How to Use This Skill
    - **Without arguments** — load the core frameworks below: the four characteristics + 18 best practices, the 12-step process, the estimating methods, risk/uncertainty, EVM, and the specialized techniques.
    - **With a topic** — ask about a characteristic ("credible"), a step ("ground rules and assumptions", "point estimate"), a method ("parametric", "learning curve"), a risk concept ("Monte Carlo", "confidence level", "contingency"), or an EVM term ("CPI", "EAC", "performance measurement baseline").
    - **With a chapter** — `ch02`/`ch03`/`ch05` (the 12 steps), `ch04` (risk/uncertainty), `ch06` (auditing), `ch07` (EVM), `ch08` (specialized techniques).
    
    Supporting files: `glossary.md`, `patterns.md`, `cheatsheet.md`.
    
    > **One discipline, two uses.** The Guide is both an **authoring** standard (how to build a reliable estimate) and an **audit** standard (how to grade one). The same four characteristics and 18 best practices serve both. EVM (ch07) is the execution-side bridge: the estimate says what a program *could* cost; EVM measures whether it is *delivering* against a baseline built from that estimate.
    
    ## Core Frameworks & Mental Models
    
    ### What a cost estimate is — and why reliability is a process, not luck
    
    A cost estimate is the sum of individual cost elements, built from established methods and valid data, projecting what a program will cost in the future given what is known now. It is not a one-time deliverable — *managing* it means revising it as actuals arrive, adjusting it when the program changes, and analyzing the gaps. The Guide's central claim: **reliability is the predictable output of a disciplined, repeatable process**, not seniority or luck. A reliable estimate matters structurally for government — every dollar committed to one program is denied to another, so an unrealistic estimate can ripple cuts across a whole portfolio.
    
    ### The Four Characteristics of a Reliable Cost Estimate
    
    GAO's research identifies four characteristics that a reliable estimate exhibits. They are the assessment yardstick auditors apply, and the design targets an estimator engineers toward:
    
    | Characteristic | What it demands |
    |---|---|
    | **Comprehensive** | full life cycle + complete scope (a complete WBS); all GR&As documented; nothing omitted or double-counted |
    | **Well documented** | sources, methods, and calculations captured so an unfamiliar analyst could rebuild it; traced to source data |
    | **Accurate** | unbiased (not optimistic or conservative); most-likely-cost basis; inflation-adjusted; reconciled to actuals |
    | **Credible** | limitations exposed via sensitivity and risk/uncertainty analysis; major drivers cross-checked; reconciled to an independent cost estimate (ICE) |
    
    The **18 best practices** are the actionable steps that produce these characteristics; each best practice maps to one characteristic. An estimate that fully reflects all four is deemed **reliable**.
    
    ### The 12-Step Cost Estimating Process
    
    The procedural backbone, grouped into four phases:
    
    - **Plan & define (Steps 1-4)**: (1) define the estimate's **purpose** — intended use fixes scope and detail; (2) develop the **estimating plan** — team, study plan, schedule; (3) define the **program** via a cost-free **technical baseline description**; (4) determine the estimating structure — the **work breakdown structure (WBS)**, the product-oriented decomposition that ties cost, schedule, EVM, and risk together.
    - **Build the number (Steps 5-7)**: (5) identify **ground rules and assumptions** (global + element-specific); (6) **obtain the data** — collect, validate, normalize (the most difficult, time-consuming step; data quality is the biggest lever); (7) develop the **point estimate** — select a method per WBS element, build the model, time-phase, sum, and cross-check against an ICE.
    - **Quantify confidence (Steps 8-9)**: (8) **sensitivity analysis** (vary one input at a time); (9) **risk and uncertainty analysis** (vary many inputs together via simulation → probability distribution + confidence level).
    - **Finalize & sustain (Steps 10-12)**: (10) **document** the estimate; (11) **present** it to management for formal approval (not finished until approved); (12) **update** it against actuals and program changes over the life cycle.
    
    Each step's chapter closes with a "Survey of Step" — Process Tasks, Best Practices, and Likely Effects if criteria are not fully met — which is what makes each step **auditable**.
    
    ### Estimating Methods
    
    Choose by program maturity and available data; the method can differ per WBS element:
    
    | Method | Use when | Trade-off |
    |---|---|---|
    | **Analogy** | early; a close similar system exists | fast, low data; weak without a good analog |
    | **Parametric** | drivers + cost history, design still vague | repeatable via cost estimating relationships (CERs); needs valid data range |
    | **Engineering build-up** | mature design | most accurate; slow and data-hungry |
    
    Supplemented by expert opinion, extrapolation from actuals (averages, EACs), and **learning curves** (Y = AX^b) for recurring production.
    
    ### Risk and Uncertainty → a risk-adjusted budget
    
    A point estimate alone carries no confidence information and tends to under-fund. **Sensitivity analysis** isolates one input at a time (ranked on a tornado chart) to find what the estimate is most responsive to. **Risk and uncertainty analysis** lets inputs vary together — via the **three-point** method (min/most-likely/max) and/or the **risk-driver** method (probability × cost effect, from the risk register) — driven by **Monte Carlo simulation**, producing a total-cost probability distribution. Reading the **cumulative distribution (S curve)** gives a defensible **confidence level**; **contingency** is sized as the gap between the point estimate and that level.
    
    ### Earned Value Management (EVM) — measuring execution
    
    Spending data alone misleads (the railroad example: looks under-budget while badly behind). EVM adds the missing third number — the *value of work performed*. Three measures: **BCWS** (planned value), **BCWP** (earned value), **ACWP** (actual cost). Derived indexes: **CPI** = BCWP/ACWP (cost), **SPI** = BCWP/BCWS (schedule), **TCPI** (efficiency needed on remaining work). The **EAC** forecasts total cost from cumulative CPI. The estimate is converted into a time-phased **performance measurement baseline (PMB)**; an **integrated baseline review (IBR)** confirms it is executable — the crucial link between cost estimating and EVM. EVM systems are validated against **EIA-748's 32 guidelines**. OMB requires EVM for major acquisitions with development effort.
    
    ### Specialized Techniques & Internal Control
    
    Beyond the 12 steps: **software cost estimating** (size first via SLOC/function points/COSMIC, convert to effort; classify code new/reused/adapted/auto-generated); **learning curves** (unit vs. cumulative-average theory; Anderlohr/retrograde for production breaks); **Analysis of Alternatives (AOA)** (22 best practices in 5 phases; NPV where benefits monetize); **WBS templates** (MIL-STD-881D, NASA/DOE/PMI handbooks); and the **Green Book** (GAO-14-704G) internal-control framework (5 components, 17 principles) — because the cost estimating process *is itself an internal control*.
    
    ---
    
    ## Chapter Index
    
    | # | Section | Key content |
    |---|---------|-------------|
    | [ch01](chapters/ch01-gao-cost-fundamentals-credible-estimates.md) | Fundamentals & the four characteristics | What a cost estimate is; reliability as process; the four characteristics; 18 best practices; 12-step process; LCCE; why government needs reliable estimates |
    | [ch02](chapters/ch02-gao-cost-process-planning-program-definition.md) | Steps 1-4: Planning & program definition | Purpose & scope; estimating plan/team; technical baseline description; the work breakdown structure (WBS) |
    | [ch03](chapters/ch03-gao-cost-data-ground-rules-point-estimate.md) | Steps 5-7: Ground rules, data, point estimate | Global vs. element-specific GR&As; data collection/validation/normalization; estimating methods (analogy/parametric/build-up); cross-checks and the ICE |
    | [ch04](chapters/ch04-gao-cost-sensitivity-risk-uncertainty.md) | Steps 8-9: Sensitivity, risk & uncertainty | Sensitivity (one-at-a-time, tornado chart); three-point & risk-driver methods; Monte Carlo; S curve, confidence level, contingency |
    | [ch05](chapters/ch05-gao-cost-document-present-update.md) | Steps 10-12: Document, present, update | Documentation template & rationale; management approval; updating against actuals and program changes |
    | [ch06](chapters/ch06-gao-cost-auditing-validating.md) | Auditing & validating | The characteristics/best practices as gradable criteria; mapping practices to characteristics; assessing agency guidance against the 12 steps; audit criteria & data collection |
    | [ch07](chapters/ch07-gao-cost-earned-value-management.md) | Earned value management | EIA-748 (32 guidelines); 13 EVM activities; PMB/IBR/CPR; BCWS/BCWP/ACWP; CPI/SPI/TCPI; EAC; OTB/OTS; EVM system acceptance |
    | [ch08](chapters/ch08-gao-cost-specialized-techniques-internal-control.md) | Specialized techniques & internal control | Software cost estimating; learning curves (Anderlohr/retrograde); WBS templates; TRLs; AOA (22 practices); the Green Book (5 components, 17 principles) |
    
    ## Topic Index
    
    - **18 best practices** → ch01, ch06, cheatsheet
    - **Accurate (characteristic)** → ch01, ch06
    - **Analogy method** → ch03, cheatsheet
    - **Analysis of Alternatives (AOA)** → ch08, ch01
    - **Anderlohr / retrograde (production break)** → ch08
    - **Audit / validation of an estimate** → ch06, patterns
    - **CPI / SPI / TCPI (performance indexes)** → ch07, cheatsheet
    - **Comprehensive (characteristic)** → ch01, ch06
    - **Confidence level / S curve** → ch04, cheatsheet
    - **Contingency / management reserve** → ch04, ch07
    - **Cost estimating relationship (CER)** → ch03, ch04
    - **Credible (characteristic)** → ch01, ch06
    - **Data collection / validation / normalization** → ch03
    - **Documentation (Step 10)** → ch05, patterns
    - **Earned value management (EVM)** → ch07, ch01, cheatsheet
    - **EIA-748 / 32 guidelines** → ch07
    - **Engineering build-up method** → ch03, cheatsheet
    - **Estimate at completion (EAC)** → ch07
    - **Four characteristics (reliable estimate)** → ch01, ch06, cheatsheet
    - **Green Book / internal control** → ch08
    - **Ground rules & assumptions (GR&A)** → ch03
    - **Independent cost estimate (ICE)** → ch03, ch05
    - **Integrated baseline review (IBR)** → ch07, ch08
    - **Learning curve (Y = AX^b)** → ch08, ch03
    - **Life cycle cost estimate (LCCE)** → ch01, ch02
    - **Monte Carlo simulation** → ch04
    - **Parametric method** → ch03, cheatsheet
    - **Performance measurement baseline (PMB)** → ch07
    - **Point estimate (Step 7)** → ch03
    - **Present / management approval (Step 11)** → ch05
    - **Risk & uncertainty analysis (Step 9)** → ch04, cheatsheet
    - **Risk driver / risk register** → ch04
    - **Sensitivity analysis (Step 8)** → ch04, cheatsheet
    - **Software cost estimating** → ch08
    - **Technical baseline description (Step 3)** → ch02
    - **Technology readiness level (TRL)** → ch08
    - **Three-point estimate** → ch04
    - **Tornado chart** → ch04
    - **12-step process** → ch02, ch03, ch04, ch05, cheatsheet
    - **Update the estimate (Step 12)** → ch05
    - **Well documented (characteristic)** → ch01, ch05, ch06
    - **Work breakdown structure (WBS)** → ch02, ch08
    - **WBS templates (MIL-STD-881D, NASA/DOE/PMI)** → ch08
    
    ## Supporting Files
    
    - [glossary.md](glossary.md) — key cost-estimating, risk, and EVM terms, alphabetical, with chapter references
    - [patterns.md](patterns.md) — reusable patterns (run the 12 steps; engineer toward the four characteristics; pick a method by maturity; convert the point estimate to a risk-adjusted budget; document/update; audit; pair with EVM; specialized techniques) with When/How/Trade-offs
    - [cheatsheet.md](cheatsheet.md) — the 12 steps, four-characteristics table, method-selection table, risk toolkit, EVM index reference, and tells & smells
    
    ---
    
    ## Scope & Limits
    
    **Covers**: program cost estimating per the GAO Cost Estimating and Assessment Guide (GAO-20-195G, March 2020) — the four characteristics of a reliable estimate and the 18 best practices; the full 12-step cost estimating process; estimating methods (analogy, parametric, engineering build-up, learning curves); sensitivity, risk, and uncertainty analysis (Monte Carlo, confidence levels, contingency); documenting, presenting, and updating; auditing/validating an estimate against the characteristics; earned value management (EIA-748, the EVM measures and indexes, PMB, IBR, EAC forecasting, system acceptance); and specialized techniques (software cost estimating, Analysis of Alternatives, WBS templates, technology readiness levels, the Green Book internal-control framework).
    
    **Thin on / does not cover in depth**: **schedule** estimating and **schedule risk analysis** — the Guide deliberately hands these to the GAO **Schedule Assessment Guide** (GAO-16-89G; see `gao-schedule`), and technology-maturity assessment to the **Technology Readiness Assessment Guide** (GAO-20-48G; see `gao-tra`). It does **not reproduce** the full text of referenced standards and frameworks — **EIA-748**, **MIL-STD-881D**, the **Green Book** (GAO-14-704G), ICEAA/AACEI/PMI standards — these are named and summarized, not copied. Embedded source figures and tables (discipline maps, WBS diagrams, worked method tables, EVM exhibits) are described/paraphrased here, not reproduced; redraw from the originals if a rendered exhibit is needed. The Guide is GAO best-practice guidance, oriented to US federal acquisitions and DoD/NASA examples; it is not a regulation, though several statutes (Weapon Systems Acquisition Reform Act, Nunn-McCurdy, FASA, Clinger-Cohen, the FAR/DFARS EVM provisions) make parts of it effectively mandatory for major acquisitions.
    
    **Jurisdiction**: US Government public domain work. The guidance is voluntary best practice but is broadly adopted and partly mandated for federal major acquisitions; it is adaptable to non-federal programs.
    